Progress of CPEC

0
# Project Name Progress Update
1 Port Qasim Electric Company Coal Fired, 2×660, Sindh · Financial Closed (FC) achieved.
· Civil works on site started in May 2015.
· Approximately 65% Power Plant and 70% Jetty completed
· Energization in October 2017.
· Expected Commercial Operation Date (COD) June 2018.
2 Sahiwal 2x660MW Coal-fired Power Plant, Punjab · Financial Closed (FC) achieved.
· Civil works on site 95% completed.
· Planned energization in October 2017.
· Commercial Operation Date (COD) 25 Dec, 2017.
· However, project is 06 months ahead of schedule i.e energization in May 2017.
3 Engro thar 4x330MW Coal-fired, Thar, Sindh · Financial Closed (FC) achieved in April, 2016.
· Team mobilized at site.
· Construction work in progress.
· Construction of Transmission line-contract awarded. Contractor mobilized
· Commercial Operation Date (COD) June, 2019
4 Surface mine in Block II of Thar Coal field, 6.5 metric ton per annum (mtpa), Thar Sindh · Financial Closed (FC) achieved.
· IA/EA signed.
· COD expected 2018/2019
5 Gwadar Coal fired Power Project, Gwadar · CCCC has registered with PPIB
· It was agreed on the proposal of Chinese side to facilitate issuance of LoI by PPIB after submission of bank guarantee and agreements with the view to start work on the project by 31st March, 2017 at the latest
6 HUBCO coal power plant 1X660 MW, Hub Balochistan · IA/EA Signed
· Commercial Operation Date (COD) expected 2018/2019
7 Rahimyar Khan Coal Power Project, Punjab · Feasibility in process
8 SSRL Thar Coal Block 1 – 6.5 metric ton per annum(mpta) Thar, Sindh · Commercial Operation Date (COD) expected 2018 / 2019
9 SSRL 2×660 MW Mine Mouth Power Plant,Sindh · Expected Commercial Operation Date (COD) 2018 / 2019
10 Zonergy 900MW Solar Park, Bahawalpur, Punjab · COD of 3 x 100 MW attained in August 2016.
11 Dawood 50MW wind Farm, Bhambore, Sindh · Financial Close (FC) achieved
· Construction started.
· Testing in Progress.
· Commercial Operation Date (COD) Jan, 2017.
12 UEP 100MW wind Farm, Jhimpir, Sindh · Construction started.
· Erection of 61 out of 66 turbines completed.
· Sub-station under construction, to be completed by March, 2017.
· Independent Engineer mobilized.
· Commercial Operation Date (COD) Expectd June, 2017
13 Sachal 50MW Wind Farm, Jhimpir, Sindh · Financial Close (FC) achieved.
· Construction in progress.
· Commercial Operation Date (COD) June, 2017
14 Suki Kinari Hydro power Station, KPK · Financial Close achieved.
· Land acquisition award announced on 17th Nov, 2016.
· EPC Contractor mobilized to initiate construction activities.
· Commercial Operation Date (COD) 2021/2022.
15 Karot Hydropower Station, AJK & Punjab · Land acquisition award done.
· Financial Close (FC) 2017.
· Construction in Progress.
· Work initiated through equity – 25% civil works completed.
· Commercial Operation Date (COD) 2020/2021.
16 Matiari to Lahore Transmission line · Feasibility study completed.
· Tariff determined by NEPRA.
· TSA/IA initialed in December 2016.
· Land acquisition for converter stations at Lahore and Matiari completed.
· China Electric Power Equipment and Technology Company(CET) / State Grid nominated by Chinese side.
· COD expected in 2018 / 2019.
17 Matiari to Faisalabad Transmission line · Feasibility study completed
· Decision on tariff review petition announced by NEPRA
· COD expected in 2018 / 2019
· TSA/IA initialed during 6th JCC
· China Electric Power Equipment and Technology Company(CET) / State Grid nominated by Chinese side
18 Gaddani Power Park Project (2×660MW) · Under Study
19 Gaddani Power Park Project (Jetty + Infrastructure) · Under Study
20 HUBCO coal power plant 1X660 MW, Hub Balochistan · IA/EA Signed.
· COD expected 2018/2019.
21 Kohala Hydel Project, AJK · Feasibility Study (stage-1) Tariff Announced by NEPRA.
· Land Acquisition process started.
· Environmental Impact Assessment study being updated.
· EPC Contractor has been selected.
· Financial close planned in Dec 2017.
· Expected Commercial Operation Date (COD) 2023.
22 Pakistan Wind Farm II 2X50 MW(Jhampir, Thatta, Sindh) · LOS issued in August 2016.
· EPA initialed on 30th Nov, 2016.
· Construction activity already started from equity.
· Financial Close April 2017.
· COD Sep, 2018.
23 Thar mine mouth oracle, Thar Sindh · Feasibility stage tariff obtained for coal.
· Shareholding agreement on new equity partners in process.
24 Muzaffargarh Coal Power Project, Punjab
25 KKH Phase II (Thakot -Havelian Section) · Contractor mobilized. Work commenced in September, 2016. To be completed by March, 2020
· Havelian- Abbotabad-Mansehra (40 KM) section will be completed by May, 2018
26 Peshawar-Karachi Motorway (Multan-Sukkur Section) · Contractor mobilized
· Construction works commenced in August, 2016
27 Expansion and reconstruction of existing Line ML-1 · Feasibility completed
· Request for Chinese financing submitted on 29th Nov, 2016
· Senior Officials to discuss and finalize modalities/terms of financing
· Both side agreed to have extensive communication in the first fortnight of Jan, 2017 to reach consensus within three months
28 Havelian Dry port (450 M. Twenty-Foot Equivalent Units) · Feasibility completed
· Request for Chinese financing submitted on 29th Nov, 2016
29 Gwadar East-Bay Expressway · Minutes of EAD-MOFCOM signed
30 New Gwadar International Airport · Minutes of EAD-MOFCOM signed in August 2016
· Grant request is being processed by Chinese Side
31 Construction of Breakwaters · Draft business plan has been received from Chinese (COPHCL), under review by MoP&S and GPA
32 Dredging of berthing areas & channels · Draft business plan has been received from Chinese (COPHCL), under review by MoP&S and GPA
33 Development of Free Zone · Tax exemptions for port and Free Zone notified in Finance Bill 2016
· Ground breaking done by the Prime Minister
· 100% private Investment inside Free Zone. To be operated by COPHCL
· 1st phase completion date is December 2017
· Significant progress and response from investors
· Gwadar Free Zone investment guide line published
34 Necessary facilities of fresh water treatment, water supply and distribution · PC-I for 5 MGD RO plant for Gwadar cleared by CDWP in Dec 2016
· Draft Framework Agreement shared with Chinese side and likely to be signed soon
35 Pak China Friendship Hospital · Grant request sent by EAD to MOFCOM
· Feasibility study completed by Chinese team to add 100 beds from existing 50, for subsequent extension to 300 beds
· LOE is expected to be signed in early 2017
36 Technical and Vocational Institute at Gwadar · Chinese technical team expected to visit early this year to conduct feasibility study
· MoU likely to be signed soon
37 Cross Border Optical Fiber Cable · Ground breaking cermony performed by the Prime Minister
· Work commenced October 2015
Work on 220km/ 820km segment completed
38 Pilot Project of Digital Terrestrial Multimedia Broadcast (DTMB) · Project completed at a cost of US$ 2 million
· As confirmed by Mo I &B LoE on demonstration project with Chinese side is being processed
39 Karachi Circular Railway · JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
· JWG on Transport Infrastructure has been asked to complete the necessary formalities
40 Greater Peshawar Region Mass Transit · JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
· JWG on Transport Infrastructure has been asked to complete the necessary formalities
41 Quetta Mass Transit · JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
· JWG on Transport Infrastructure has been asked to complete the necessary formalities
42 Orange Line – Lahore
43 Keti Bunder Sea Port Development Project · Further studies and consultations to be initiated
· Projects referred to concerned JWGs for consideration
44 Naukundi-Mashkhel-Panjgur Road Project connecting with M-8 & N-85 · Further studies and consultations to be initiated
· Projects referred to concerned JWGs for consideration
45 Chitral CPEC link road from Gilgit, Shandor, Chitral to Chakdara · Further studies and consultations to be initiated
· Projects referred to concerned JWGs for consideration
46 Mirpur – Muzaffarabad – Mansehra Road Construction for connectivity with CPEC route · Further studies and consultations to be initiated
· Projects referred to concerned JWGs for consideration
47 Quetta Water Supply Scheme from Pat feeder Canal, Balochistan · Relevant Provincial Govts. to work out proposals on implementation of projects
48 Iron Ore Mining, Processing & Steel Mills complex at Chiniot, Punjab · Relevant Provincial Govts. to work out proposals on implementation of projects
49 Rashakai Economic Zone on M-1 · Work on SEZs to be initiated on priority
50 Special Economic Zone Dhabeji · Work on SEZs to be initiated on priority
51 Bostan Industrial Zone · Work on SEZs to be initiated on priority
52 Punjab – China Economic Zone, M-2 District Sheikhupura · Work on SEZs to be initiated on priority
53 ICT Model Industrial Zone, Islamabad · Work on SEZs to be initiated on priority
54 Development of Industrial Park on Pakistan Steel Mills Land at Port Qasim near Karachi · Work on SEZs to be initiated on priority
55 Bhimber Industrial Zone · Work on SEZs to be initiated on priority
56 Mohmand Marble City · Work on SEZs to be initiated on priority
57 People to People exchanges · Efforts for intensification of People to People contact, media and cultural exchanges (including movies, drama, theatre etc.) would be done through agreed yearly programmes. Both sides resolved to promote Chinese and Pakistani culture and heritage as a way of long term partnership
58 Transfer of Knowledge in different sectors · Experts from Industrial zones, rural and urban development, job creation & SMEs, water resources management & treatment and agriculture
59 Gwadar Smart Port City Master Plan · LOE signed in August 2016
· Name of one Consultant received by EAD. The case is being processed on fast track to ensure completion within twelve months
60 Bao Steel Park, petrochemicals, stainless steel and other industries in Gwadar · Necessary approval process would be completed at the earliest for inclusion as new CPEC Project under Gwadar JWG
61 Development of Gwadar University (Social Sector Development) · Chinese side will identify a leading Chinese university for collaboration with University of Gwadar on marine & maritime related subjects along with other disciplines
62 Upgradation and development of fishing, boat making and maintenance services to protect and promote livelihoods of local population · COPHCL would take effective measures for social sector development
63 Moqpondass SEZ Gilgit-Baltistan · Work on SEZs to be initiated on priority
64 Khuzdar-Basima Road N-30 (110 km) · Procedural formalities to be completed shortly
65 Upgradation of D.I.Khan – Zhob, N-50 Phase-I (210 km) · Procedural formalities to be completed shortly
66 KKH Thakot-Raikot N35 remaining portion (136 Km) · Procedural formalities to be completed shortly
67 Capacity Development of Pakistan Railways · Focus groups be established for effective training and capacity enhancement